Pilot uranium mining at site No. 3 of the Budyonovskoye deposit (South Kazakhstan)

Process pumping station, sand settlers for production and barren solutions, on-site and off-site process communications, sulphuric acid warehouse with a pumping station, overpass, first-aid point, administrative and utility building, checkpoint, radioactive waste site, diesel fuel tanks, on-site and off-site power networks, low-voltage networks, septic tank, boiler house, utility, drinking and fire-fighting tanks and a pumping station, first-lift pumping station, process water tanks, water intake wells, on-site water supply and sewerage networks, heating networks, road, fencing, landscaping, planting and asphalting of the site.

  • Concrete1 910 m³
  • Metal structures178 t
  • Sandwich panels950 m²

About the project

  • Years of work
    2010–2011
  • Customer
    АО «СП «Акбастау» (АО «НАК «Казатомпром»)
  • TOP Ltd LLP
    General contractor