Khorgos — Eastern Gate SEZ

Comprehensive works on the Dry Port and infrastructure facilities of the Khorgos — Eastern Gate special economic zone

A second-lift pumping station, checkpoint, external power networks, on-site water supply and sewerage networks, chlorination house, drilling of 2 exploration wells of 300 m and 10 water intake wells of 250 m, 6 fire-fighting water reserve tanks, fencing, process pipelines, sewage collector, sewage pumping stations No. 2, 3, 4 and 5 delivering wastewater for post-treatment, post-treatment modules, grit chamber, a compact modular biological treatment unit, a sludge site of two cells, an emergency regulating tank, video surveillance, perimeter security alarm, comprehensive process automation, external heating networks, septic tank and external water supply networks V1 and V2.

About the project

  • Years of work
    2014–2016
  • Customer
    ТОО «АБК-Автодор НС» (АО «НК «Казахстан Темир Жолы»)
  • TOP Ltd LLP
    Contractor

Photo gallery